CALPADS error brief · MEET
MEET0426
Official CALPADS rule
What CALPADS is rejecting
If Meeting Activity - Evaluation Type Code = 15 or 10 AND Special Education Meeting Date is greater than 60 days from the Initial Evaluation Parental Consent Date THEN the Meeting Delay Code must be populated.
Focus fields
Fields validated
24.12 - Initial Evaluation Parental Consent Date 24.13 - Special Education Meeting Date 24.16 - Meeting Activity - Evaluation Type Code 24.15 - Meeting Delay CodeRecommended correction path
Suggested resolution
Official rule in plain language
Severity: Fatal Type: Input Validation
Fields validated
- 24.12 Parental Consent Date
- 24.13 Meeting Date
- 24.15 Meeting Delay Code
- 24.16 Evaluation Type Code
The code explains why the reported timeline was exceeded; it does not make the delay compliant. Part C and Part C-to-B scenarios also have additional timing rules beyond this CALPADS trigger.
Delay reporting follows the underlying activity
Current Meeting Delay codes
| Code | Reason | Important scope |
|---|---|---|
| 10 | Delay in Parental Consent | Activity-specific consent or agreed reevaluation circumstances. |
| 15 | Exceptional Family Circumstances | Part C Initial; effective beginning 2025–26. |
| 20 | Parent/child unavailable | Repeated documented unavailability. |
| 25 | Late Referral to Part C | Part C-to-B third-birthday scenario; effective beginning 2025–26. |
| 30 | Parent contacted—did not attend | Plan review, including reevaluation + plan review. |
| 40 | School Break | Initial Part B 60-day context. |
| 50 | Transfer | Initial Part B, reevaluation, or plan review as permitted. |
| 60 | School emergency/closure | Permitted activity combinations. |
| 70 | Student/family emergency | Permitted activity combinations. |
| 80 | Due process/settlement | Permitted activity combinations. |
| 85 | Hearing/vision screening | Initial Part B or reevaluation; not plan-review-only. |
| 90 | Late Without Cause | Use when no supported exception explains the delay. |
Concrete checks
- Calculate elapsed days from the correct consent and meeting dates.
- Verify evaluation type 10 or 15.
- Select a current delay code permitted for that activity/year.
- Preserve documentation; never choose a more favorable reason than the evidence supports.
Recommended correction path
- 1
Preserve the rejected row
Capture submission ID, SSID, Reporting LEA/SELPA, Academic Year, all MEET dates, activity indicators, outcome, delay, and the ODS history.
- 2
Identify the event state
Determine whether the activity was pending or completed and whether it involved an initial evaluation, reevaluation, plan review, or combination permitted by Version 18.
- 3
Build the chronology
Place referral, consent, pending checkpoints, meeting, determination, delay, SWDS, and PLAN events in order.
- 4
Verify governing evidence
Use signed meeting/evaluation records, procedural documentation, the SEDS, and the current code/combination definitions. Do not infer an outcome or delay reason.
- 5
Correct the source and mapping
Correct erroneous dates/type, or populate the evidence-supported current delay code. A true late-without-cause event should be reported honestly as Code 90. Repair any recurring export rule.
- 6
Resubmit and reconcile
Confirm acceptance, inspect the complete MEET history, and review connected SWDS/PLAN records and affected reporting results.